Deyaar Midtown Raft Completion at Zone 3
Deyaar Midtown Zone 3 raft have been completed earlier by 40 days from the due date; total casted concrete 26 195 cubic meter divided to six pours; pouring sequence was as per the work program commenced on 12th September 2017 and completed on 20th December 2017 .